The measurement area is expected to be traversed from the end of this week. The vibro-trucks will move slowly and incrementally through the area – much like a travelling roadworks site. Every 30 metres, they generate sound waves through controlled vibrations, which are recorded by the geophones. This enables us to gather data on the geological structure beneath the ground. These measurements will take place over several weeks.
Where exactly will the measurements take place? The project is very dynamic. We will publish updates on the progress and schedule of the measurements on our website as far as possible. We ask for your understanding that there may be traffic restrictions whilst the work is in progress.
Thank you very much for your support!